Sumaré East datacenter construction update

Microsoft began constructing the Sumaré East datacenter in July 2023. The datacenter construction site is located on Estrada Municipal Valencio Calegari in Sumaré, State of São Paulo.
Why datacenters are needed
Datacenters provide the physical infrastructure for the technology we depend on at work and in our personal lives. Whenever you open an app on your phone, join a virtual classroom or meeting, snap and save photos, or play a game with your friends online, you are using a datacenter. Local businesses, government, hospitals, and schools rely on datacenters every day to deliver goods and services to you.
Construction update 4 June 2025
The general contractor Racional carries out most of its activities from Monday to Saturday, from 7am to 7pm, occasionally working on Sundays on internal activities with less impact or until 10pm during the week. Racional is currently engaged in the following activities:
- Site preparation: mostly completed.
- Walls raised and covered: mostly completed.
- Internal installations: under development, expected to be completed in the second half of 2025.
- Substation: mostly completed.
- Definitive gatehouse: expected to be completed in the second half of 2025.
- Offsite activities: under development, expected to be completed in the second half of 2025.
Construction timeline
Datacenter construction began in July 2023 and is estimated to be complete in early 2028. The general contractor Racional is permitted to work Monday through Friday from 7am until 5pm and Saturdays from 7am until 2pm. Infrequently, teams may need to work until 10pm. Racional is currently engaged in the following activities:
- Installation of metal structure and walls, from September 2023 to mid 2024
- Substation construction, from October 2023 to late 2024
Together with our general contractor Racional, we will keep neighbors informed in advance of construction work.
Staying connected
We will keep the community up to date via our Brazil: Greater Campinas page in our Microsoft in Your Community blog.
For daily operational questions, you can also reach out to the contractor at contato.r604@racional.com or by phone at (011) 95628-6239.