Conover – Lyle Creek datacenter construction update

A young female construction worker using a laptop

Microsoft is building a datacenter in the greater Conover, North Carolina area near Highway 16 in Catawba County.

Why datacenters are needed

Datacenters provide the physical infrastructure for the technology we depend on at work and in our personal lives. Whenever you open an app on your phone, join a virtual classroom or meeting, snap and save photos, or play a game with your friends online, you are using a datacenter. Local businesses, government, hospitals, and schools rely on datacenters every day to deliver goods and services to you.

September 2026: Construction update

Work continues to move forward on the first building at the Lyle Creek datacenter site, with key milestones achieved on the building structure and exterior.

The building exterior is in its final stages of completion. Framing and drywall work has started and continues to progress throughout the building. Work on underground infrastructure also continues to support the site and upcoming equipment deliveries.

Mechanical and electrical work has begun, and additional interior work continues. Work is also beginning on additional building areas to support upcoming phases of construction.

We appreciate the community’s patience as construction progresses and will continue to provide updates on significant milestones.

May 2026: Construction update

Work is advancing across multiple areas of the site, with key milestones reached in foundations and early structural development. 

Construction activity is moving forward as crews complete early phases and begin vertical construction: 

  • Underground work, foundations, and slab installation are complete for several buildings. 
  • Steel installation has begun on site, marking the start of above-ground construction. 
  • Additional buildings are progressing through foundation and footing stages as site-wide development continues.  
  • Telecommunications infrastructure work is underway in multiple areas to support future operations. 

February 2026: Construction update

At the Lyle Creek site, Microsoft’s general contractor, Whiting‑Turner, will begin initial site preparation once weather conditions allow. Early activities will include installing fencing, preparing the site, and limited paving work to support temporary facilities.

Foundation work is expected to begin in mid‑March, following completion of site preparation activities.

Construction hours

Construction activity is expected to take place from Monday to Friday, 7:00 AM to 6:00 PM. Work hours will follow local permitting requirements.

May 2024: Construction timeline

Datacenter construction began in March 2024. The general contractor Morgan Corp is preparing the site by excavating and crushing rock onsite. In some cases this involves controlled blasting in the early afternoon to break apart larger rocks.

Together with our general contractor Morgan Corp we will keep neighbors informed in advance of construction work.

Staying connected

We will keep the community up to date via our North Carolina page in our Microsoft in your community blog.

As of February 2026, our general contractor is Whiting-Turner. For construction related questions, please fill out this form, Lyle Creek Datacenter Campus.

If you have any additional questions, please contact the Microsoft Community Affairs Manager at northcarolinadc@microsoft.com or leave a voicemail at 980-776-2251.